Sanigad Hydro located along the right bank of the Kalanga River in the Seti zone of the Far-Western Region, the project leverages the river’s flow, partly sustained by snowmelt, making a significant contribution to Nepal’s sustainable energy landscape.

Contact Us

Silent Features

Salient Feature:

The brief salient features of the project as described in the PPA documents are;

  1. Project Name: Upper Kalanga Hydro Electric Project (UKHEP)
  2. Project Area: Bungal Municipality, Bajhang
  3. Source: Kalanga gad khola
  4. Project Type: RoR
  5. Project Capacity: 38.46 MW
  6. Catchment area at HW: 162.68 Sq. km
  7. Design Discharge: 7.99 m3/sec
  8. Gross Head: 585.50 m
  9. Weir: Length – 35 m , Height – 4.3 m
  10. Desanding Basin: Length – 130 m
  11. Conveyance: Headrace canal, Box Culvert of total length 920 m and cross section 2.7 m x 2.3 m
  12. Penstock: 1500 meter, diameter 1.55 m and thickness of 22 mm
  13. Powerhouse: The powerhouse is of size 40m x 30m x 25m
  14. Turbine: Vertical Axis Pelton 3 unit, turbine axis in level of 1182.5 m elevation.
  15. Generating Units: Three units of 3 phase synchronous Generator of 50 Hz of Frequency and Generation Voltage of 11 KV.
  16. Head Race Tunnel: 6478m of 2.5m dia of inverted D-shape
  17. PPA and Energy: Total annual contract energy of 219.390018 GWb, 180.318988 GWh wet and 39.071030 GWb dry
  18. Project Cost NRs 8,687 million
  19. Commercial Operation Date: Falgun 06, 2079